New Bulkhead Construction

Building a bulkhead where there was not one before, or rebuilding on a new alignment. Here is how the work actually runs, start to finish.

New bulkhead construction is the most involved thing we do on a residential shoreline, and it is the work where the difference between contractors shows up years later rather than on handover day. Anyone can make a wall look right on the day it is finished. Making it still look right after a decade of tide cycles, storm surge and soil pressure is the actual job.

Before anything gets built

The quality of a bulkhead is largely decided before a pile goes in the ground.

Survey and alignment. We establish where the wall is going relative to your property line and the water. On a replacement this is also where we work out whether building in front of the existing wall is viable or whether the old structure comes out.

Soils. What is behind and beneath the wall determines embedment depth, tieback design, and in some cases the material choice. Sandy soils, organic layers and the depth to firm bearing all change the engineering.

Exposure. A sheltered creek frontage and a stretch of open river with fetch and boat wake are different design problems, even if they are a mile apart. Exposure drives cap elevation and how the toe is protected.

Loads behind the wall. A lawn is one thing. A driveway, a pool deck, or a structure near the top of the slope is a surcharge load, and the wall has to be designed for it. This is one of the most commonly missed items on a cheap estimate.

Permitting. Review can involve FDEP, the U.S. Army Corps of Engineers, the St. Johns River Water Management District and your county or city building department. Requirements vary by site and are revised periodically — confirm current requirements with the reviewing agency. We handle the permitting on the projects we build, and the permit timeline is normally the longest item on the schedule.

How we build

  1. Mobilization and protection. Equipment access is planned around your property. On tight residential lots this is a real constraint and sometimes decides the construction method.
  2. Driving the sheet piles. The piles are driven to design embedment, panel by panel, with the interlocks engaged so the wall acts as a continuous structure rather than a row of separate boards. Alignment is held as the wall advances — a wall that wanders is a wall that will have joint problems.
  3. Tiebacks and anchors. Tieback rods are installed through the wall and run back to deadman anchors set in undisturbed soil at a depth and distance that puts them outside the active soil wedge. Getting the anchor placement wrong is a quiet failure: the wall looks finished and the tiebacks do nothing.
  4. The cap. The concrete cap ties the tops of the piles together, distributes load along the wall, and gives you the finished edge you actually walk on. It is formed, reinforced and poured as a structural element.
  5. Backfill and drainage. Backfill is placed and compacted in lifts. Filter fabric and a drainage detail at the joints let water out without taking soil with it — this single detail is the difference between a wall that holds your yard and a wall that slowly exports it.
  6. Finish and cleanup. Grading, restoration of the disturbed area, and a walkthrough.

Material choice at the construction stage

New construction is where you get a free choice of material, which is not true of a repair. The three we build in:

  • Vinyl sheet pile — the default for most residential First Coast shorelines. Will not rot or corrode, and the tieback system does the structural work.
  • Concrete — the heaviest and longest-lived option, and the usual choice where the wall also serves as a finished architectural edge or where loads are high.
  • Wood — treated timber, lowest initial cost, and the right call when you are matching an existing structure or working a sheltered location on a tighter budget.

The cost page explains how those choices move the estimate.

If you have an existing wall

Not every property that asks for new construction needs it. If you have a wall that is failing, start with bulkhead repair and bulkhead replacement — the second one covers how we decide between the two. A marine inspection gives you that answer in writing, with the condition of the elements you cannot see from the top.

Call (904) 327-3931 or request a free estimate. We will come out, look at what you actually have, and tell you what the site needs.

Frequently asked questions

How deep do bulkhead sheet piles have to go?
Embedment depth is an engineering decision, not a rule of thumb. It depends on the height of soil being retained, the soil type and its strength, the water elevation on each side, and the surcharge load behind the wall — a driveway behind a bulkhead changes the answer. The design embedment comes out of the engineering for your specific site.
What are tiebacks and why does my wall need them?
A tieback is a rod or cable running from the wall back into your yard to an anchor — usually a buried deadman. It resists the horizontal push of the retained soil. Without tiebacks, a wall of any meaningful height is relying entirely on the embedded portion of the piles to resist that push, which limits how much soil it can hold back. Most residential bulkheads on the First Coast are tied back.
Can you build a bulkhead in front of my failing one?
Sometimes, and it can be an attractive option because it avoids demolishing the old wall. It is not automatic: it moves your structure waterward, which has permitting consequences, and the new alignment has to make sense for your site. It is one of the options we look at during an estimate.

Last reviewed October 2026 by Barefoot Marine Construction. Permit requirements and agency rules change — confirm current requirements with the reviewing agency before you plan work.

What customers say about this work

Unedited reviews from our Google Business Profile, where all 22 can be read in full.

Read them on Google
  • Apparently Barefoot Marine Construction has only good employees. While they built our wall there were two different crews working and every one of their guys was professional and skilled. They always seemed to be busy and we couldn't be happier with the result.

    Jackie Lunsford

    5 years ago Google review

  • Rick and crew showed up during a very trying time when our bulkhead contractor, having demolished our existing bulkhead, proceeded to go bankrupt. We were left stranded with no warning and no protection from erosion to our yard.

    Rick's crew immediately went to work stabilizing the shoreline.

    They went above and beyond to work with our previously approved permit and engineering and even used the already purchased vinyl sheeting onsite. We did not feel any stress during the build, the crew showed up every morning on time, and kept the site clean and organized. They actually worked and did not stand around half the day drinking pop and playing with their phone. The price was competitive, the workmanship was excellent, and the billing was always fair and honest - we never felt over exposed. Rick takes a lot of pride in his work and wants his customers to be just as happy. This is our fourth bulkhead and you will not find a better contractor.

    Tom Snyder

    2 years ago Google review

  • Rick and his team were outstanding in our bulkhead repair. We had another company do a full bulkhead replacement in 2020. The bulkhead failed within months and had to be replaced (again). Same company performed the second replacement, and didn't construct an appropriate anchor/ tie back system, which caused movement in the wall. I hired Rick and his team to come in and repair the existing bulkhead. They created an anchor system that will hold the bulkhead in place well beyond the lifespan of the vinyl pilings they are anchoring. Rick was professional, fair, and his team was very respectful of our property. I give Rick and Barefoot Marine Construction our highest recommendation.

    Matthew McCullough

    a year ago Google review

Get a free estimate on your project

Send us a few photos and what you're seeing, and we'll tell you what it needs — repair, replacement, or just monitoring.

Certified General Contractor #1533461 · Workers' Comp + USL&H Insured · Serving Northeast Florida since 2009